| Line item | Bid A ████████████ | Price | Bid B ████████████ | Price | Bid C ████████████ | Price |
|---|---|---|---|---|---|---|
| Tear-off and disposal | 1 layer only; 2nd layer extra | ███████ | Up to 2 layers | ███████ | Up to 2 layers | ███████ |
| Underlayment | 30# felt, field only | ███████ | Synthetic, full coverage | ███████ | Synthetic + ice & water at eaves, valleys, penetrations | ███████ |
| Shingles, installed (210 squares) | Architectural, 30-yr limited | ████████ | Class 4 impact-rated architectural | ████████ | Designer architectural, lifetime limited | ████████ |
| Flashing, drip edge, pipe boots | New drip edge and boots; REUSES step flashing | ██████ | All new, incl. chimney counter-flashing | ███████ | All new | ███████ |
| Ridge and ventilation | New ridge cap; existing vents reused | ██████ | Ridge vent + new box vents (balanced) | ██████ | Ridge vent + new box vents | ██████ |
| Decking repair (rotted sheathing) | EXCLUDED; ████ if found | — | Allowance: 40 sheets; overage ████ | ██████ | EXCLUDED; time and materials | — |
| Gutters and downspouts | Excluded | not priced | Excluded | not priced | New gutters and downspouts included | ███████ |
| Dumpsters and site protection | Included | ██████ | Included | bundled | Included | bundled |
| Permit and inspections | EXCLUDED | — | Included | ██████ | Included | ██████ |
| Overhead and profit | Lump sum | ███████ | Lump sum | ███████ | Lump sum | ███████ |
| TOTAL AS BID | ████████ | ████████ | ████████ |
| Bid | Adjustment to match reference scope | Amount |
|---|---|---|
| Bid A ████████████ | Total as bid | ████████ |
| 2nd-layer tear-off allowance (210 sq x ████) | ██████ | |
| Synthetic underlayment upgrade (210 sq x ████) | ██████ | |
| Ice & water at eaves, valleys, penetrations | ██████ | |
| Replace reused step flashing | ██████ | |
| Balanced ventilation upgrade | ██████ | |
| Decking allowance, 40 sheets x ████ | ██████ | |
| Permit and inspections | ██████ | |
| LEVELED TOTAL, Bid A | ████████ | |
| Bid B ████████████ | Total as bid | ████████ |
| Ice & water at eaves, valleys, penetrations | ██████ | |
| LEVELED TOTAL, Bid B | ████████ | |
| Bid C ████████████ | Total as bid | ████████ |
| Remove gutters (not in reference scope) | ████████ | |
| Decking allowance, 40 sheets x ████ (T&M estimate) | ██████ | |
| LEVELED TOTAL, Bid C | ████████ |
| Bid | Issue | Why it matters |
|---|---|---|
| A | Excludes decking repair (billed per sheet if found) | Open-ended cost, usually discovered mid-job after the contract is signed. |
| A | Felt underlayment, field only; no ice & water shield | Leaks at eaves and valleys are the most common failure point. The shingle warranty may require better underlayment. |
| A | Reuses existing step flashing | Old flashing is where most leaks start. A new roof over old flashing can void the manufacturer warranty. |
| A | Excludes permit; only 1 layer of tear-off priced | Board pays for the permit separately. A hidden 2nd layer is an unpriced change order. |
| B | Decking allowance 40 sheets, overage ████ | Fair structure, but the overage rate is above A's. Negotiate it down. |
| B | Gutters excluded | Fine for this scope, but the Board should decide separately whether to replace them. |
| C | Decking repair on time and materials, no cap | No ceiling on a cost that could be large. |
| C | Gutter replacement bundled in | Inflates the headline. Not in the reference scope, so we removed it from the leveled total. |
| C | Materials escalation clause over 5%; price good 15 days | The price can rise after signing. Short validity forces a rushed vote. |
| Term | Bid A | Bid B | Bid C |
|---|---|---|---|
| Workmanship warranty | 2 years | 10 years | 10 years |
| Manufacturer warranty | Shingle only; system warranty not offered | Full system warranty; contractor is a certified installer | Full system warranty; certified installer |
| General liability | $1M per occurrence; no umbrella | $2M per occurrence + $5M umbrella | $1M per occurrence + $2M umbrella |
| Workers' comp certificate | Not provided | Attached | Attached |
| Association named as additional insured | Not stated | Yes | Yes |
| Payment terms | 50% deposit, 50% at completion | 20% deposit, 60% progress, 20% retainage until final inspection | 40% deposit, 60% at completion |
| Price valid for | 30 days | 60 days | 15 days; escalation clause |
| Schedule | Start in 3 weeks, 3 weeks on site | Start in 6 weeks, 4 weeks on site | Start in 8 weeks, 4 weeks on site |
This is a comparison of the documents provided, built for board decision support. It is not legal, engineering or insurance advice. Figures come only from the bids supplied; adders are estimates for comparison. The Board should verify licenses, insurance certificates and warranty terms directly with each contractor and with the association's counsel or insurance agent. Northpoint Ventures · northpointvc@proton.me